Hazlehead Academy’s new campus reaches steel-frame milestone

Author: 1 min read

Crane lifts a steel beam as Hazlehead Academy’s new campus reaches its steel-frame milestone

The new Hazlehead Academy campus will provide space for up to 1,600 pupils and serve an expanded catchment in west Aberdeen. Its steel frame has now been completed, marking a major step in the £124million project.

Construction and opening plans

  • Work began in March 2026, with around 80 truckloads of steel delivered to the site in August.
  • Aberdeen City Council, hub North Scotland and Robertson Construction representatives joined the head teacher and pupils to sign the frame before it is enclosed.
  • The campus is being built on the existing school’s playing fields, allowing the academy to remain open during construction.
  • The new facility is scheduled to open in August 2028. Demolition of the current school buildings and completion of external sports facilities are expected by summer 2029.
  • Plans include two full-size all-weather pitches, an athletics sprint track and an expanded catchment covering Hazlehead, Countesswells and Kingswells.

The campus is one of Aberdeen City Council’s largest school estate projects and the first school being built through hub North Scotland’s North Schools Programme. Project partners say it will provide modern learning facilities and support employment and skills development.

Councillors Alex McLellan and Martin Greig, hub North Scotland project director Scott Adams and Robertson Group chief executive Elliot Robertson welcomed the construction progress. McLellan said: “The completion of the steel frame is an important milestone in the delivery of the new Hazlehead Academy Campus and demonstrates the progress being made on this major investment.”